21 February 2024 |
Maha Metro Nagpur celebrates 10th Foundation Week; Foundation Week observed between 14th to 21st February. Winners from various sports events and employees and officials with exemplary services felicitated and awarded. |
2 February 2024 |
City’s First ever `Shared Autorickshaw Service’ started by Nagpur Metro from Kasturchand Park Metro Station at the hands of Maha Metro MD Shri Sharavn Hardikar. Nagpur Municipal Corporation (NMC) starts Shuttle Bus Service between Nagpur Airport and Airport Metro Station. |
22 November 2023 |
Formal launch of the works for 2nd Phase of Nagpur Metro Rail Project at the hands of Maha Metro MD Shri Sharavn Hardikar. |
27 October 2023 |
16th Urban Mobility India (UMI) Conference gets underway at Delhi; Maha Metro stall inaugurated by Union Minister for Housing and Urban Affairs Shri Hardeep Singh Puri. |
20 October 2023 |
Nagpur Metro logs in a record ridership of 1.13 lakh on account of Dussehra, Dhamma Chakra Pravartan Din, Raas-Garba. |
14 October 2023 |
Union Minister Shri Nitin Gadkari and other dignitaries performed Bhoomi Pujan of the proposed ₹ 80 crore underpass from Manas Square to Institute of Science, to be constructed by Maha Metro Nagpur. |
01 October 2023 |
Cleanliness campaign `Swachhta hi Sewa’ as part of National Mission executed by Maha Metro. |
30 September 2023 |
MoU for Phase-II of Nagpur Metro Rail Project signed between Maha Metro, Government of India (GoI) and Government of Maharashtra (GoM). |
21 September 2023 |
Cotton Market Metro Station becomes operational. |
17 August 2023 |
Tekdi flyover demolition over. |
15 Aug 2023 |
Independence Day celebrated at Metro Bhawan. |
14 August 2023 |
Partition Horror Day exhibition inaugurated by MD and Freedom Fighters at Sitabuldi Interchange. |
28 July 2023 |
Senior IAS officer Shri Shravan Hardikar assumed charge as Managing Director of Maharashtra Metro Rail Corporation Limited from Dr Nitin Karir. |
28 July 2023 |
Senior IAS officer Shri Shravan Hardikar assumed charge as Managing Director of Maharashtra Metro Rail Corporation Limited from Dr Nitin Karir. |
28 July 2023 |
Tekdi flyover demolition begins. |
5 June 2023 |
Maha Metro celebrated Environment Day on 5th June by planting and distributing saplings at Little Wood and Metro Stations respectively. |
15 May 2023 |
Maha Metro MD Dr Brijesh Dixit has handed over the charge to the Additional Chief Secretary (Finance), Government of Maharashtra Dr Nitin Karir, today (15th May 2023). Dr Dixit presided over Maha Metro for over 8 years and has been responsible for the successful completion of Nagpur Metro Phase-I, start of Phase-II and partial execution of the Pune Metro Rail Project. |
27 April 2023 |
A 6-member team of the Asian Development Bank (ADB) visited Nagpur Metro Project and inspected the completed Phase-I of the Nagpur Metro Project and sought information about Phase-II. |
12 April 2023 |
Construction Industry Development Council (CIDC), which is part of NITI Aayog presented Vishwakarma Best Officer Award to MD Dr Dixit at an event held in New Delhi. The award was presented by Shri PS Rana, Chairman, CIDC. |
1 April 2023 |
Hon Union Minister Shri Nitin Gadkari, Hon Deputy Chief Minister Shri Devendra Fadanvis and other dignitaries inaugurated Navin Loha Pul and Ram Jhula Extension Flyover. |
19 March 2023 |
The Hon Deputy Chief Minister of Maharashtra Shri Devendra Fadanvis presented certification and citation for three Asia Book of Records – `Longest Length of Metro Rail Corridor Construction in Shortest Time’, `First Solar PV System in a Metro Rail Project for Integrated Consumption’ and `Heaviest Single Span Double Decker Steel Bridge Truss over Railway tracks in Urban Area’, in Asia to MD Dr Dixit at Metro Bhawan. |
14 March 2023 |
A meet of entrepreneurs and businessmen of all categories was held at Metro Bhavan, to give them information about Small and Large Spaces. |
18 February 2023 |
Maha Metro Nagpur celebrates 9th Foundation Day. |
13 February 2023 |
A delegation of Construction Industry Development Council (CIDC) which is part of NITI Aayog visited Metro Bhavan to study Nagpur Metro Rail Project. |
9 February 2023 |
The Probationary officers of Indian Administrative Services (IAS) visited Metro Bhawan to have a first-hand glimpse of the project and to understand its basic working. |
31 January 2023 |
The National Academy of Indian Railways (NAIR) felicitates and confers the prestigious Distinguished Alumnus Award on MD Dr Dixit, at an event held at Vadodara. |
26 January 2023 |
Nagpur Metro logs second best ridership at 1.96 lakh. |
26 January 2023 |
74th Republic Day celebrated at Metro Bhawan. |
25 January 2023 |
Nagpur Metro bags 13 awards at the 48th Flower Exhibition organized by Parks and Gardens Wing of PWD, Nagpur. |
21 January 2023 |
AM Cinema’s multiplex opens at Jai Prakash Nagar Metro Station – the first ever in the Metro Station premises. |
25 December 2022 |
Nagpur Metro logs 1.66 lakh ridership, second highest till date. |
23 December 2022 |
Former Chief Minister Shri Prithviraj Chavan visited Metro Bhavan
and also took Metro Ride. |
23 December 2022 |
The secretary to Hon Deputy Chief Minister Devendra Fadnavis
and senor administrative Officer Shri Shrikar Pardeshi today visited Metro Bhavan and
also took Metro Ride. |
22 December 2022 |
The Additional Chief Secretary (Chief Minister Secretariat & Urban Development-I) Shri Bhushan Gagrani and his team of officials took a Metro Ride. |
11 December 2022 |
The Hon. Prime Minister Shri Narendra Modi, flagged off
inaugural metro trains from Automotive Square to Kasturchand Park Metro Station
(Orange Line) and Prajapati Nagar to Sitabuldi Interchange (Aqua Line). The Prime Minister, dedicated first phase of Nagpur Metro Rail Project and laid Foundation Stone
for the second phase of Nagpur Metro Rail Project. |
07 December 2022 |
Maha Metro conferred with Guinness World of Records title for
Wardha Road Double Decker Via-duct which has been identified by Guinness World
Records as the Longest Double Decker in the Metro category across the world. |
24 November 2022 |
A 4-member team of Asian Development Bank (ADB) officials were on
3-day visit of Nagpur Metro Rail Project. |
13 November 2022 |
The Divisional Commissioner, Nagpur Division Smt Vijayalakshmi Bidari took a Metro Ride. Smt Bidari traveled on the scenic Aqua Line between Sitabuldi Interchange and Lokmanya Nagar |
06 November 2022 |
Maha Metro was awarded second prize in the `Best Exhibitor’ category at the 15th UMI National Conference |
06 November 2022 |
The Governor of Kerala Hon Arif Mohammad Khan visited the Maha Metro stall at the UMI |
04 November 2022 |
The 3-day 14th Urban Mobility India (UMI) Conference gets underway at Kochi, Kerala.The Maha Metro Stall at the venue was inaugurated by Union Minister for Housing and Urban Affairs Shri Hardeep Singh Puri, inaugurated the Nagpur Metro Stall. Kerala Chief Minister Shri Pinarayi Vijayan, who was Chief Guest at the event, was present online |
28 October 2022 |
Maha Metro`s Nagpur Metro Facebook page crossed 7 lakh likes mark |
14 October 2022 |
Maha Metro MD Dr Brijesh Dixit gave away 20th Construction World Global Awards (CWGA) 2022 at a glittering ceremony held at ITC Grand Central in Mumbai. Part of the 8th India Construction Festival and organized by FIRST Construction Council, the Awards honors companies from the universe of construction, contracting, engineering and building materials, for their outstanding work |
10 October 2022 |
The District Collector, Nagpur Shri Vipin Itankar had a Metro Ride. He travelled to and fro from Lokmanya Nagar Metro Station and Sitabuldi Interchange |
04 October 2022 |
A 3-member team of European Investment Bank (EIB) Officials visited Nagpur Metro Project |
17 September 2022 |
Maha Metro MD Dr Brijesh Dixit conferred with Special Lifetime Achievement Award by Engineers’ Forum for his contribution in the field of Infrastructure & Engineering |
11 September 2022 |
Maha Metro MD Dr. Brijesh Dixit was felicitated at 4th World Record Holders’ Meet held at New Delhi for being chosen in top 100 record holders for excellence in world stage 2022 at New Delhi. Dr Dixit was presented with the Privilege Certificate of Distinct Honour and Praise |
06 September 2022 |
Geospatial World conferred `Excellence Award for Metro Project’ on Maha Metro Nagpur. The award was presented at the hands of Union Minister of State for Road Transport & Highways and Civil Aviation Gen (Retd) VK Singh at the GeoSmart India conference held at New Delhi |
15 August 2022 |
Maha Metro logs record ridership of 90,758 |
15 July 2022 |
Maha Metro MD Dr Brijesh Dixit conferred with the prestigious 'Special Lifetime Achievement Award' for his selfless service in the field of infrastructure development by Indian Institute of Bridge Engineers (IIBE) |
26 June 2022 |
The Confederation of All India Traders (CAIT) felicitated and conferred Maha Metro`s MD, Dr. Brijesh Dixit with prestigious Bhamashah Award |
04 May 2022 |
CMRS (Commissioner of Metro Rail Safety) conducted inspection at Hingna Mount View Car Depot. |
29 April 2022 |
CMRS (Commissioner of Metro Rail Safety) conducted inspection & testing of Reach-2 (Kasturchand to Automotive Square) section & stations of this reach |
15 April 2022 |
No Of Nagpur Metro Passengers crosses 45,000 Mark |
29 March 2022 |
Historic Movement as Gaddigodam Bridge Crossed for the First Time. Maiden Ride Between Kasturchand Park and Automotive Square Metro Station |
23 March 2022 |
Rajya Sabha Member Shri Praful Patel rides Metro Train, visits Metro Bhavan. |
15 March 2022 |
Team of officials from AFD France and KfW Germany on 2-day inspection visit of Nagpur Metro Project. |
14 March 2022 |
Maha Metro MD Dr Brijesh Dixit inspects work progress at Gaddigodam crossing location. |
05 March 2022 |
Maha Metro, MD, Dr. Brijesh Dixit was felicitated for his exemplary contribution in providing world-class and affordable Transportation Services in Nagpur. |
21 February 2022 |
CMRS is conducted inspection & testing of Reach-4 Central Avenue section & stations of this reach. |
18 February 2022 |
Maha Metro, Nagpur celebrated its 7th Foundation Day |
27 January 2022 |
Advertising agreement has been signed between Life Insurance Company of India and Maha Metro |
01 January 2022 |
Metro’s Record Ridership at 51,670 on New Year Day |
22 December 2021 |
India`s largest double decker girder launched at Gaddigodam |
30 October 2021 |
Maha Metro Bags ‘Excellence in Urban Transport’ Award. Metro Gets Recognition for Best Multi-Modal Integration |
29 September 2021 |
Quality Conclave organized by Maha Metro for its, Contractors’ and General Consultants at Metro Bhavan. MD Dr Brijesh Dixit addressed the gathering. |
21 September 2021 |
Yet another milestone for Maha Metro Nagpur as it crosses 6.5 lakh likes on its Facebook page. Nagpur and Pune Metro Facebook page collective likes stand at 12,62,700. |
20 August 2021 |
Zero Mile Freedom Park - Kasturchand Park stretch, Zero Mile station and Kasturchand Park station and the public park named Freedom Park is inaugurated by Hon. CM Shri Uddhav Thackeray and Hon. Union Ministers Shri Nitin Gadkari and Shri Hardeep Singh Puri. |
06 August 2021 |
The Commissioner of Metro Rail Safety (CMRS) gives sanction for Zero
Mile Freedom Park Station and Kasturchand Park Metro Stations. |
02 August 2021 |
A team of CMRS reaches Nagpur for inspection of Zero Mile Freedom
Park Station, Kasturchand Park and other Nagpur project work. |
14 July 2021 |
Maharashtra Minister for Sports, Youth Welfare, Animal Husbandry and Milk
Production Shri Sunil Kedar visited Metro Bhavan. |
04 June 2021 |
Ajni Metro Station Bags IGBC Platinum Rating Certificate. Becomes 14th station to get this Certification. |
03 June 2021 |
Maha Metro MD Dr Brijesh Dixit inspects project work at Balanced Cantilever Bridge (Reach-IV) and Gaddigodam Metro Station and 4-Layer Transportation structure at Gaddigodam |
02 June 2021 |
Maha Metro MD Dr Brijesh Dixit inspects project work at Depot |
02 June 2021 |
Maha Metro successfully held trial run of Metro train on Reach II between Zero Mile Freedom Park and Kasturchand Park stations |
06 April 2021 |
Passenger services started from Ujwal Nagar, Chhatrapati Nagar, Congress Nagar & Dharampeth College Metro Stations |
31 March 2021 |
Commissioner of Metro Rail Safety (CMRS) clears commercial services of Ujwal Nagar, Chhatrapati Nagar, Congress Nagar & Dharampeth College Metro Stations. |
26 March 2021 |
Commissioner of Metro Rail Safety (CMRS) Shri Janak Kumar Garg on day-long visit to inspect Ujwal Nagar, Chhatrapati Nagar, Congress Nagar and Dharampeth College Metro Stations. |
25 March 2021 |
Public Investment Board (PIB) clears Nasik Metro Neo Project proposal to be sent to Government of India, at an investment of ₹ 2,092 crore |
09 March 2021 |
Maha Metro MD Dr Brijesh Dixit inspects Prajapati Nagar Metro Station project work |
08 March 2021 |
An amount of ₹ 188.95 crore and ₹ 302.19 crore respectively, proposed for Nagpur and Pune Metro Rail projects by Maharashtra Finance Minister Hon Shri Ajit Pawar in state budget |
03 March 2021 |
Cab on Call service from Khapri Metro Service to MIHAN launched. |
22 February 2021 |
Maha Metro services on Aqua Line advanced to 06.30 am instead of 08.00 am. |
18 February 2021 |
6th Foundation Day of Maha Metro Nagpur celebrated. Airport to Airport Metro Station feeder service flagged off by MD Dr Brijesh Dixit |
09 February 2021 |
The divisional commissioner Shri Sanjeev Kumar visits Nagpur Metro Project, holds discussion with officials. |
09 February 2021 |
A high-power delegation from France, led by French Ambassador His Excellency (Mr) Emmanuel Lenain visited Nagpur Metro project. |
05 February 2021 |
The Director General (Information & Public Relations), Government of Maharashtra Shri Dilip Pandharpatte takes ride on Aqua Line |
01 February 2021 |
An amount of ₹ 5,976 and ₹ 2,092 proposed respectively for Nagpur Metro Phase-II & Nasik Metro Neo in the Union Budget by Union Finance Minister Hon Smt Nirmala Sitaraman. |
26 January 2021 |
Republic Day celebrated at Metro Bhavan. Maha Metro clocks a historic and record-breaking ridership of 56,406 |
24 January 2021 |
Maha Metro MD Dr Brijesh Dixit addresses `Metro Maha-Samwaad’ organized by Unnati Foundation and Chhatra Jagruti. |
12 January 2021 |
City Mayor Shri Daya Shankar Tiwari pays courtesy visit to Metro Bhavan. |
09 January 2021 |
Maha Metro Nagpur Facebook Page crosses 6 lakh likes mark |
27 December 2020 |
Nagpur Metro reached this years highest metro travel ridership |
08 December 2020 |
Nagpur Metro received certificate for Shankar Nagar Square and Rachna Ring Road Junction Metro Station |
31 October 2020 |
Maha Metro Nagpur received the prestigious IGBC Platinum Green Building rating for Sitaburdi Interchange Station |
20 October 2020 |
Maha Metro, Local Auto Body Join Hands to Provide Last Mile Connectivity |
15 October 2020 |
Dr. Brijesh Dixit, MD, Maha Metro conferred with the Person of the Year Award 2020 - Public Sector at 18th Construction World Award. |
14 October 2020 |
Maha Metro achieved a major milestone when it received a certificate from Commissioner of Metro Rail Safety (CMRS) to Ajni Square, Rahate Colony, LAD and Bansi Nagar Metro Station |
12 October 2020 |
Nagpur Metro received the prestigious Indian Green Building Council ( IGBC ) Platinum Rating |
14 August 2020 |
Maha Metro, TiE jointly hosted Webinar on Business Opportunities With Maha Metro |
26 June 2020 |
The Nagpur District Guardian Minister Dr Nitin Raut visits Metro Bhavan, discusses project-related work.
|
04 June 2020 |
Maha Metro Nagpur awarded ISO 14001:2015 Certificate.
|
06 April 2020 |
Maha Metro Nagpur Facebook Page crosses 5.50 lakh mark.
|
23 March 2020 |
Maha Metro contributes ₹ 12 lakh towards Chief Minister Relief Fund towards COVID-19 relief measures.
|
14 March 2020 |
The Department of Heavy Industries, Ministry of Power, Government of India permits Energy Efficient Services Limited (EESL) to install Electric Vehicle (EV) charger at Metro Stations.
|
12 March 2020 |
Passenger services on Aqua Line every 15 minutes. |
26 February 2020 |
Work on Maha Metro’s Gaddigodam Multi-Layer Transport System Begins |
28 January 2020 |
Maha Metro Aqua Line services between Lokmanya Nagar Metro Station
and Sitabuldi Interchange inaugurated by Shri Uddhav Thackeray, Chief Minister, Shri
Nitin Gadkari, Union Minister, Shri Hardeep Singh Puri, Union Minister, in the presence
of Maharashtra ministers – Shri Eknath Shinde, PWD Minister, Shri Anil Deshmukh,
Home Minister, Shri Nitin Raut, Energy Minister, Shri Sunil Kedar, Youth Welfare
Minister and other dignitaries. |
23 January 2020 |
Bio Digesters has been installed at Khapri, New Airport and Airport South Metro Stations |
18 January 2020 |
Nagpur Metro Received CMRS Certificate for Vasudev Nagar Metro Station |
17 January 2020 |
CMRS conducts inspection for Vasudev Nagar Metro Station, grants certification for it. |
07 January 2020 |
Track Laying work has been started Between Kasturchand Park & Zero Mile Station |
24 December 2019 |
The Commissioner of Metro Rail Safety (CMRS) conducted inspection related to the all-important Communication-Based Train Control (CBTC) technology along Reach-III stretch between Lokmanaya Nagar Metro Station and Sitabuldi Interchange |
13 December 2019 |
CMRS Conducted Inspection of Jhansi Rani Metro Station |
10 December 2019 |
Maha Metro has been awarded DPR work preparation for Metro Neo project in Warangal, State of Telangana |
02 December 2019 |
Maha Metro has successfully commissioned `Pit Wheel Lathe’ (PWL) at MIHAN Rolling Stock Depot |
27 November 2019 |
Maha Metro starts operations every 15 minutes at 80 KMPH |
22 November 2019 |
CMRS clears Metro train travel at 80 KMPH |
20 November 2019 |
Jai Prakash Nagar – the sixth Metro Station opens for public |
19 November 2019 |
A high-power delegation from State of Telangana met Maha Metro officials and sought help in executing similar project in their state. |
14 November 2019 |
CMRS team begins 2-day inspection of Maha Metro project |
12 November 2019 |
Railway Board clears Metro train run at 80 KMPH |
10 November 2019 |
AfD France & KfW Germany begin 3-day visit of Maha Metro project |
05 November 2019 |
Maha Metro gets nod from National Highway Authority of India (NHAI) for fly-over over Kamptee Road |
04 November 2019 |
The last segment (2393) for Reach-IV being cast at Asoli workshop |
26 September 2019 |
Airport, Jai Prakash Nagar and Rahate Coloy Metro Stations get IGBC’s Platinum Rating. |
19 September 2019 |
Maha Metro starts train services every half an hour. |
12 September 2019 |
Maha Metro Nagpur conducts Trial Run Demo at 90 KMPH between Khapri and Sitabuldi Interchange with RDSO on board. |
06 September 2019 |
Maha Metro & Kinetic Green Sign MoU for e-rickshaw
|
05 September 2019 |
Maha Metro Nagpur bags CMRS Certification for Aqua Line from Lokmanya Nagar Metro Station to Sitabuldi Interchange. |
03 September 2019 |
CMRS team begins 3-day inspection of Nagpur Metro Project. |
31 August 2019 |
Release of Maha Card & Launch of Maha Metro Mobile Application for Nagpur
Metro Commuters. |
15 August 2019 |
Independence Day Celebrations. First Trial Run from Subhash Nagar to
Sitabuldi Interchange. |
13 August 2019 |
The first Receiving Sub-Station (RSS) is inaugurated at Morris College Ground. |
08 August 2019 |
MoU for making metro stations charging station Signed between Maha
Metro and Energy Efficiency Service Limited, a Government of India enterprise. |
04 July 2019 |
500k Likes is achieved on Nagpur Metro facebook page |
27 June 2019 |
Hourly services on UP and Down line started, Total 25 services a day |
23 June 2019 |
Mazi Metro`s Up line got CMRS certificate |
04 June 2019 |
Cross Over Sitabuldi Interchange to Zero Mile |
30 May 2019 |
1st Trial Run of Reach – 3 |
10 March 2019 |
Passenger Service Started |
08 March 2018 |
Thanks Giving ( Aabhar) Metro Ride for citizens & Woman’s Day Special Ride |
05 March 2019 |
Maha Metro achieved a major milestone as it received a certificate from Commissioner of Metro Rail Safety (CMRS) |
24 Feb 2019 |
Maha Metro Nagpur bags RDSO certificate |
18 February 2019 |
RDSO done successful trial run from Khapri Metro Station to Congress Nagar Metro Station on the elevated track. |
14 February 2019 |
Honble MD Maha Metro Dr Brijesh Dixit along with Directors Mahesh Kumar and Sunil Mathur Conducted Safety run of Nagpur Metro with the Help of BULAND, Between Airport Station to Jaiprakash Nagar Station |
12 February 2019 |
First Steel I girder erection at Gowari fly over |
01 February 2019 |
MD. Dr Brijesh Dixit launched India`s first smart urban mobility solution for the public |
25 January 2019 |
Nagpur Metro has organised Dhavnaar Mazi Metro Samwad Ridership Campaign at Mahindra & Mahindra Campus Near Lokmanya Nagar, Hingna Road, Nagpur |
15 January 2019 |
Historical MoU Signed between Maha Metro & NMC for Joint Development of Markets |
08 January 2019 |
State Cabinet approves second phase of Nagpur Metro Rail Project |
26 December 2018 |
Metro Samwad conducted at Persistent Technologies, IT Park. |
24 December 2018 |
The first batch of 33 new recruits join Maha-Metro. |
20 December 2018 |
Maha- Metro and NMC sign MoU for Metro Mall Construction on Orange City Street.
Dr. Brijesh Dixit, MD, Maha-Metro and Municipal Commissioner, Nagpur, Shri Abhijit Bangar ink the pact. |
14 December 2018 |
Metro Samwad conducted at Hadas High School, North Ambazari road. |
13 December 2018 |
Completion of last foundation at Reach III achieved. |
12 December 2018 |
Launching of the last segment of Reach I completed. |
30 November 2018 |
Metro Samwad conducted at Bajaj Nagar. |
23 November 2018 |
Maha-Metro marks its presence in Agrovison 2018 through a novel way of a working train model and Priority section metro stations at their innovative stall. |
22 November 2018 |
Shri Brijesh Dixit, Honble MD, Maha-Metro inspected and flagged off the first metro train of Nagpur Metro Rail Project at CRRC Dalian plant, China for dispatch to Nagpur. |
12 November 2018 |
Nagpur Metro Rail Project felicitated at Indian Green Building Congress -2018 for achieving the highest (Platinum) rating for its three stations at the hands of Shri Hardeep Singh Puri, Honble Minister, Housing & Urban Affairs |
04 November 2018 |
Maha Metro Wins Prize For `The Best Exhibitor` At UMI 2018. |
02 November 2018 |
The 11th Urban Mobility Conference (UMI) Was Inaugurated By The Chief Minister Of Maharashtra Devendra Fadnavis At Chitanvis Centre. |
01 November 2018 |
The First Safety Park In India, Conceived By Maha-Metro, Was Inaugurated At The Hands Of Shri Durga Shankar Mishra, Housing And Urban Affairs Secretary Of India. |
24 October 2018 |
Ramzula phase II work which was under Metro scope has been successfully completed in all respects |
22 October 2018 |
Ground floor slab completed at Engineering Train Unit Building Hingna Depot |
19 October 2018 |
50% of Pre Casting work at Aasoli Casting Yard for Reach IV completed. |
12 October 2018 |
Work for last segment of the double Decker flyover between Airport South station and Munje square completed. |
12 October 2018 |
Last Metro Segment casting of reach-1 is completed. |
02 October 2018 |
Zero Mile Metro Station
Basement 1 and 2 work completed.
Ground level slab 86% completed and
Mezzanine Level slab 32% completed. |
30 September 2018 |
Nagpur Metro for the first time plied at the peak speed of 90 Kms per hour.
|
22 September 2018 |
Agrasen Metro Station - Agrasan station pier arm and second stage pier and pier cap casting completed,segment erection work in Agrasen station is in progress. |
10 September 2018 |
RDSO gives permission for 90 KM/hr trial run for Nagpur Metro.
|
03 September 2018 |
Casting Yard - Asoli, Bhandara Road -T & Rectangular Girders Scope / Completed - 754 / 299
Segment casting Scope / Completed - 2378 / 1037
Erection completed - 653 ( 50 spans) |
31 August 2018 |
Metro Sanwad at PWS college Kamathi Road |
25 August 2018 |
Tree plantation for 6000 trees kicked off at Little Woods II in around 139 acres area. There is a plan to have a plantation of around 11000 trees in this area.
|
24 August 2018 |
Airport Metro Station - UP & Down line platform construction completed. PEB structure Erection 50/430 completed. |
20 August 2018 |
Road safety week started |
05 August 2018 |
The work of establishing track at Hingna Depot is continue,Total 4 km track will be created at Hingna Depot out of which 350 meters tracks work was completed. |
21 July 2018 |
Track Work started in Lokmanya nagar area and Rachana ring road on Metro Viaduct Standard gauge up line & down line.
A Metro Samwad was conducted at Goyal Ganga Building, Munje Chauk, Sitabuldi on Saturday 21st of July 2018.
24 July An amazing Metro Sanwad of Metro Friends and Fans was conducted with Lupin Limited At Mihan |
17 July 2018 |
Railway, Maha Metro and Maharashtra Government signed MoU to connect Wardha, Ramtek, Katol and Bhandara. |
12 July 2018 |
Successful demonstration of Buland on the elevated section after successful testing on the land - The 1.5 km of track work is completed from the airport south to the airport metro station on the elevated section, and the bulland shutter engine has been officially demonstrated on this track to deal with this track. |
04 July 2018 |
Handing over of operational rooms for system works at Reach-3 Subhash nagar station and Lokmanya nagar Station |
30 June 2018 |
Maha-Metro has organized Metro Samwad at Shahapurkar Hall, Dharampeth |
24 June 2018 |
Peoples Representatives first ride of Nagpur Metro |
22 June 2018 |
The first segment of Reach - 2 on Metro Viaduct Section, D&B Portion, between Zero Mile Station and Sitabuldi Station (Near Patwardan School, Sitabuldi) was launched successfully. |
18 June 2018 |
Dr. Brijesh Dixit, MD, Maha Metro gets the "Rotary Vocational Excellence Award" |
13 June 2018 |
Prepare for DPR presentation of Nagpur Metro Phase II |
04 June 2018 |
Nagpur Metro Rail Project have added another #Feather in its cap by officially receiving the plaques and confirming the Platinum rating for three metro stations of priority section namely South Airport, New Air Port and Khapri. Platinum rating is the highest rating for metro stations awarded as per IGBC Green MRTS rating system. |
26 May 2018 |
Concourse level slab Post tensioning rib beam slab Total 19 rib 5 main bay + 1 loading & unloading bay Span width of 27.2 mtr Total length 81.95 mtr
09 rib beams completed out of total 19. |
22 May 2018 |
Fifth pour of Basement -1 level slab of Zero Mile station has been caste, with this pour of concrete, 4800 sqm out of 5300 sqm has been caste at Zero Mile Metro Station at Basement – 1 level. |
19 May 2018 |
Foundation Work (Pile Cap Reinforcement) at Pier Location P244 between Munje Chowk to Variety Chowk for Viaduct Portion in #Reach_2. Staging Work for Fixing Pier Reinforcement at Pier Location P245. |
17 May 2018 |
Pile Foundation Construction Work Started for Central Viaduct Portion of Gaddigodam Metro Station. |
17 May 2018 |
Metro Samvad & Skating Rally Held at Central Avenue, Gandhibag |
15 May 2018 |
Sitabuldi to Automotive Square corridor -
Construction of Elevated Viaduct in Reach-2 between Pier Location P231/P232 at Sitabuldi - Assembly of Ground Support Trestle (Underslung) by Hydraulic Crane for Span Erection |
04 May 2018 |
Nagpur Metro Rail Project has come up with yet another first in the city with a specially designed Hash Tag crafted to showcase the vibrancy associated with the Project. Hon’ble MD, MahaMetro Shri. Brijesh Dixit did the honors of the inauguration. |
03 May 2018 |
A delegation of KfW – the German government-owned development bank financing Nagpur Metro project – visited to Maha Metro |
26 April 2018 |
Pile Cap Exacavation & Shoring Work is in progress at P245 between Variety Chowk and Munje Chowk Viaduct Portion. |
25 April 2018 |
Hingna Casting Yard
101 Nos. out of 514 Nos. I-Girder Casting Completed for Station Portion in Reach-2 at Hingana Casting Yard. |
21 April 2018 |
First Pre-Launch ride with Under privileged People and Celebrity Marathi Actor Sachin Pilgaonkar & Swapnil Joshi |
21 April 2018 |
Automotive Corridor Viaduct work
1st Pier Cap of Metro Viaduct Level at Pier Location P230 Near Sitabuldi cast on 20.04.2018 in Reach-2 |
19 April 2018 |
Airport Metro Station Update
1st elevated station casting of 1st part of concourse level loading & unloading slab successfully completed. |
18 April 2018 |
CMRS Inspection Over, Decks Clear for Joy Ride
The second and final inspection of Maha Metro Nagpur project was undertaken by a Commissioner of Metro Rail Safety (CMRS) |
17 April 2018 |
Segment erection work from Chitaroli Chowk to Agrasen Chowk in progress
15 number of span erection completed (in segments 167 segment erected)
Length of segment - 3mts .
Width of segment -8.5 mts |
16 April 2018 |
Maha Metro, Nagpur has been Conferred with the prestigious SAP ACE Award. The award was presented at a glittering function held at Parel, Mumbai. The award was Conferred on Nagpur Metro for its pioneering work in the field of 5D BIM.
|
12 April 2018 |
Achievement - 501 numbers Out of 1630 Piles Completed for Viaduct Section near Kadbi Chowk |
11 April 2018 |
became most followed FB page among all the Metro Rail projects in India. |
09 April 2018 |
Maha Metro officials organised Metro Samwad at Gurudwara Area on Kamathi Road on 09th April 2018 |
06 April 2018 |
Total 60 "I" girder erected at Institution Of Engineers Metro Station. First concourse deck slab between sp1-sp2 casting completed Successfully on 22nd march 2018 |
30 March 2018 |
Metro Samwad program being conducted in Anjuman College of Engineering and Technology, Mangalwari bazaar road, Sadar, Nagpur, The students and faculty members actively participated in the discussion. |
28 March 2018 |
Pune Media as study tour visited to Nagpur Metro Rail Project |
27 March 2018 |
The work of ROB is visible over the ground now. U-Trough work for Manish Nagar is 80% completed and the procurement works for U-trough accessories is under procurement.
|
23 March 2018 |
An amazing "Metro Samwad" of Metro Friends and Fans was conducted at Little Wood, Hingna road on Friday. Nagpur Metro`s ongoing construction activities on the stretch of Sitabuldi to Lokmanya Nagar. |
22 March 2018 |
New Airport Metro Station - 90% ground level work is done at At-Grade area of the priority section |
17 March 2018 |
MSRDC Ramjhula - as per scope 5 no span casting completed, ramp retaining wall casting completed ramp portion filling work and crash barrier work is in progress |
17 March 2018 |
MSRDC Ramjhula - as per scope 5 no span casting completed, ramp retaining wall casting completed ramp portion filling work and crash barrier work is in progress |
06 March 2018 |
Cantilever wings (7m wide 4Lane) were launched by MahaMetro on either side of the central spine of Nagpur Metro`s 3.41 km double-decker viaduct which is being built on Wardha Road as part of the 22.293 km Line-1 between Automotive Square and Metro City. |
22 February 2018 |
Maha Metro Starts Welding of Rails in Hingna Corridor Reach 3. |
19 February 2018 |
MAHA METRO participated in the Magnetic Maharashtra Convergence 2018. |
17 February 2018 |
Maha Metro Celebrate 3rd Foundation Day. |
8 February 2018 |
First Pier concrete P-230 started at Zero Mile on Reach 2 of Sitabuldi to Automotive square Corridor by M/S Afcons. |
5 February 2018 |
National Safety Week was observed in Maha Metro. |
3 February 2018 |
Maha-Metro conducted a meeting and open discussion with Stakeholders. |
19 January 2018 |
Nagpur Metro was organised a Metro Samvad at Shankarlal Jalan Foundation, Bhandara road. |
18 January 2017 |
KFW Team Visits Nagpur Metro Project. |
17 January 2018 |
CMRS Team Visited Maha Metro Nagpur Project and Inspects Facilities |
15 January 2018 |
Maha Metro Celebrated Road Safety Week awareness program from 08th to 14th Jan 2018 with staff, workforce, and local public... |
13 January 2018 |
Maha Metro Nagpur launches first TETRA Tower |
30 December 2017 |
RDSO approval for the re-designed tubular portal by Maha Metro |
20 December 2017 |
Additional Metro Rail Coaches Arrive in Nagpur |
18 December 2017 |
400k Likes is achieved on Nagpur Metro facebook page |
06 December 2017 |
RDSO has issued the speed certificate for operation of trains between Khapri and Airport South metro stations. |
05 December 2017 |
Nagpur Metrop is organised Metro Samvad at Sitabuldi on 05 Dec 2017 |
30 November 2017 |
Stage is set for the commercial run of Nagpur Metro on a segment with the arrival of Automatic Fare Collection (AFC) gates. To be installed at the three priority stations of Airport South, New Airport and Khapri initially - the AFC gates would revolutionize travel in Nagpur. A demonstration of AFC gates was conducted
|
27 November 2017 |
Pukeshwar and Geeta watgure emerged as the fastest athletes in the 21 km MahaMetro Nagpur Marathon on Sunday, 26th Nov. The prizes all the four races were distributed by World Boxing Champion MC Mary Kom. Dr. Brijesh Dixit, Managing Directer, MahaMetro Presided over the ceremony. |
24 November 2017 |
MahaMetro has completed the casting of 1000 segments as a part of Reach-3. The East-West corridor will have 10 stations and 10.2 Km Viaduct route operating in between Jhansi Rani Square to Lokmanya Nagar. “M/s AFCONS Infrastructure Ltd.” and Team are working on this site. |
22 November 2017 |
Hon. Brijesh Dikshit, MD Maha Metro was the key speaker in joint venture of Unnati Foundation and Chhatra Jagruti on 'Maha Metro : yesterday, Today and Tomorrow' mahaSanwad held at Dhanwate sabhagruh, shankar nagar on tuesday. Dr. Dixit being honoured for getting PhD. in Economics of Safety on Indian Railway by Organisers. |
16 November 2017 |
Nagpur Metro was organised a Metro Samvad at Vyapari Association, Indora Square |
07 November 2017 |
Maha Metro has been chosen for the central urban development ministrys award for the countrys best urban mobility project. |
30 October 2017 |
Nagpur Metro has executed concrete pour of 2200 Cu. Mtr for administrative building at Mihan Depot |
16 October 2017 |
Maha Metro erected its 4th and last Steel Girder at Ramzula Section |
30 September 2017 |
Flag off the trial run of Majhi Metro and the launch a Smart Mobility card - Maha Card, at the hands of CM Devendra Fadnavis and Union Minister Nitin Gadkari |
24 September 2017 |
First steel girder erection completed out of 4 steel girders above Ramjhula |
18 September 2017 |
A Final test done by Nagpur Metro for Trial Run. Maha Metro successfully Run Buland (The Electrical shunting vehicle utilized for Track testing) between Mihan Depot to Khapari Metro station. |
07 September 2017 |
A team of "Research Design and Standard Organization (RDSO)" and Maha-Metro did a joint inspection of At Grade Section |
05 September 2017 |
On the auspicious occasion of Anant Chaturdashi, Shri Brijesh Dixit,Hon MD.Maha Metro performed bhumipujan of Eco Park at Mihan |
04 September 2017 |
Shri Brijesh Dixit, Honble MD, MahaMetro did an inspection by Rail Trolley of the track on which coaches will be seen running |
20 August 2017 |
Maha-Metro Rail Corporation is executing the biggest concrete pour at Zero Mile Station. |
14 August 2017 |
A Traction Substation (TSS) was inaugurated by Hon. Brijesh Dixit, Managing Director Maha Metro. |
02 August 2017 |
Three metro bogies arrived in the city for trial run. |
10 July 2017 |
Maha-Metro BIM Advancement Academy started at Nagpur under the stewardship of Mr. Brijesh Dixit, MD Maha-Metro. |
08 June 2017 |
Bhumi Pujan of Reach conducted 4 at the hands of Shri Brijesh Dixit, Hon. Managing Director, MahaMetro. |
01 June 2017 |
Head hardened rail for Nagpur Metro rail project arrived from Russia. |
04 May 2017 |
Nagpur Metro Facebook Page Received 3, 00,000 likes |
01 May 2017 |
Bhumi Pujan of Signaling System was performed at Khapari Station at the hands of Shri Brijesh Dixit, Hon. Managing Director, MahaMetro. |
19 April 2017 |
Sahyog Kendra Started in front of Yashwant stadium. |
13 April 2017 |
First Pier of Jhansi Rani square to Lokmanya nagar reach of East-west Corridor erected. |
10 April 2017 |
Shri Brijesh Dixit, MD, MAHA Metro inaugurated the testing facility and laboratory, which is a Joint Venture between MAHA-METRO and Bureau Veritas, at Nagpur. |
07 April 2017 |
Nagpur Metro participated in "Smart City Summit 2017" conducted at Nagpur. |
24 March 2017 |
The Work contract for the 7.657 Km stretch between Munje chowk to Projatpati Nagar is awarded to M/s ITD Cementation India Ltd. |
15 March 2017 |
Work of Nagpur Metro starts at Munje Sq. |
18 February 2017 |
Honble MD, Shri Brijesh Dixit, inaugurated "Metro Mahiti Kendra" at LIC sqaure. |
10 February 2017 |
The tender for Roof Top Solar PV Project (from stage of Designing to Testing & Commissioning and including Comprehensive Maintenance) in Metro Bhawan - the corporate office building of Nagpur Metro, has been awarded to consortium of M/S. Option Sales Pvt Ltd,M/S Welspun Energy Pvt Ltd & M/S Hygrid Solar Pvt Ltd. |
01 February 2017 |
The work of Signaling and Train Control of Nagpur Metro is awarded to Consortium of M/s SIEMENS Ltd India & Siemens Rail Automation, Spain. |
31 January 2017 |
The Raft Foundation of Airport Station Ancillary Building has been laid. |
27 January 2017 |
Nagpur Metros segment erection work at Pride Hotel junction has been completed. |
24 January 2017 |
Maharashtra Metro Rail Corporation Limited finally and formally comes into existence by reconstitution of Nagpur Metro Rail Corporation Limited. |
18 January 2017 |
LOI for Design, manufacture, Supply, Installation, testing and commissioning of Signalling and Train Control System awarded to M/S. Siemens Roll Automation, S.A.U. |
14 January 2017 |
Nagpur Metro Facebook Page Received 2, 50,000 likes |
12 January 2017 |
The rails for at-grade section arrived at Nagpur. |
12 January 2017 |
Shri Brijesh Dixit, MD, NMRCL inaugurated Nagpur Metro's stall at Comp-Ex
2017. The stall highlights were IT applications adopted by NMRCL. |
28 December 2016 |
LOI for Construction of NHAI Flyover originating from Ujjwal Nagar on the North-South corridor of Nagpur Metro Rail Project to Manish Nagar in Nagpur awarded to M/s NCC Ltd |
19 December 2016 |
Bhoomipujan For Construction Of MIHAN Rolling Stock Depot For N-S Corridor Performed On 19/12/2016. |
09 December 2016 |
LOI for Design, Engineering, Manufacture, Supply, Storage Civil work, Erection, Testing & Commissioning of the Rooftop Solar PV project including O&M at Metro Bhawan awarded to M/s. Option Sales Pvt Ltd, M/s Welspun Energy Pvt Ltd & M/s Hygrid Solar Pvt Ltd. |
1 December 2016 |
Bhoomipujan for construction of Reach 3 Viaduct between Jhansi Rani Sq and Lokmanya Nagar performed on 01/12/2016 |
30 November 2016 |
LoI for Construction of Metro Train Depot at MIHAN (N-S corridor) & Hingna (E-W Corridor) including Civil & E&M Works awarded to M/s Pratibha CSL Sudhir Constructions JV |
17 November 2016 |
Funding Agreement of 130 Million Euros for NMRCL project signed betweeb DEA and AFD France |
28 October 2016 |
LOI for Design and Construction of viaduct on reach-3 between Jhansi Rani Square to Lokmanya Nagar Stations on E-W corridor of Nagpur Metro Project awarded to AFCONS infrastructure ltd |
15 October 2016 |
LoA for Manufacture and Supply of Passenger Rolling Stock for Nagpur Metro Project signed between NMRCL and CRRC, China , in the presence of Hon. Union Minister For Surface Transport and Shipping - Shri Nitin Gadkari, Hon. Chief Minister of Maharashtra - Shri. Devendra Fadnavis, Hon. MD - NMRCL - Shri. Brijesh Dixit and other dignitaries. |
06 October 2016 |
Bhoomipujan of Dharampeth(Ambazari) Metro station was performed by Hon. M D of NMRCL |
20 September 2016 |
LoI for construction of 10 Nos Elevated Metro Stations (excluding Via-duct) on the E-W Corridor in Reach-3 awarded to ITD Cementation |
02 September 2016 |
Bhoomipujan of New Airport metro Station performed by Hon. MD of NMRCL
|
17 August 2016 |
First Segment of Via-duct Launch completed on N-S Corridor between Cargo Terminus Road and Pride Hotel Square |
12 August 2016 |
Bhoomipujan of Khapri metro station performed by Hon. MD of NMRCL |
27 July 2016 |
MoU With Bureau Veritas India To Set Up And Jointly Run World Class NMRCL-BVIL Laboratory For Testing Of Material Used In Construction And Other Civil Works. |
24 July 2016 |
MOU Signed Between NMRCL & DRDO |
23 July 2016 |
Metrosamvad- A Public Interaction Program Was Organised At Wainganga College Of Engineering . Dignitaries Present On The Occasion Were Vice Principal Surbhi Shrivastava , CEO Of College Dr. Rohit Manjule, HR & Corporate Relation Mr. Pravin Wat |
21 July 2016 |
Construction of 7 elevated metro stations and 3 At grade stations at the N-S corridor awarded to IL&FS ECC Ltd |
1 July 2016 |
Tree Plantation Program at Vasudev Nagar in Ambazari Tank submergence area. |
29 June 2016 |
Team Metro organised Metrosamvad with Taffic Police Department at DCP Traffic Office, Present on occasion were DGM (PR) NMRCL Shri. Shrish Apte , Security Advisor NMRCL Shri. Arvind Giri |
27 Jun 2016 |
As a symbol of Solar initiative of Nagpur Metro, a Battery Operated Vehicle named SOLARPULSE ONE chargeable on Solar power launched at the hands of, Honourable Chief Minister of Maharashtra, Shri. Devendraji Fadnavis. |
11 June 2016 |
NMRCL organised Metrosamvad at Datta Mandir Parsodi, Dakshin Paschim Nagpur Jeshta Nagrik Sangh. Present were President Sri. Kate, Shri. S.M. Apte DGM (PR) & other office bearers. |
31 May 2016 |
NMRCL organised Metrosamvad at MIHAN |
27 May 2016 |
NMRCL & Baljagat jointly organised Metrosamvad & Chitrakala Spardha |
25 May 2016 |
NMRCL conducted Metrosamvad at VIA on 25th May 2016. Present on the occasion were Mr. Atul Pande,President VIA ; Mr. Rohit Agarwal ,Secretary VIA; Mr. Sunil Mathur, Director (Rolling Stock) NMRCL; Mr. S. M. Apte, DGM (PR)NMRCL & Mr. Vinod Kumar Nagar JGM (Stores) NMRCL. |
14 May 2016 |
Hon. Brijesh Dixit M.D NMRCL inaugurated sample collection center for Quality Control Laboratory |
20 April 2016 |
The first Pier of elevated corridor is constructed on Wardha Road. The pier is based on Pile foundation with 4 no. of piles having diameter of 1.2mtr each. On the top of Pile foundation is Pile cap of Size 5.7x5.7. The Pier size is 1.5 mtr x2.00 mtr. & Height of Pier is nearly 8.5 mtr. The grade of concrete is M 60. |
10 April 2016 |
The Project agreement with Kfw was signed on 10th April 2016 by Hon. Managing Director, Mr.Brijesh Dixit & Director, Kfw India,Mr. Peter Hilliges |
06 April 2016 |
NMRCL conducted Metrosamvad at Eastern Sports Club |
01 April 2016 |
Agreement Signed between DEA & KFW Bank of Rs 3750 Cr for Nagpur Metro Rail at Delhi |
28 March 2016 |
NMRCL conducted "Metrosamvad"- A Public Interaction Program at G S College, Nagpur.Happy to received such a good response from students & Faculty members.They were so curious & interactive. S.M. Apte, D.G.M (P.R), NMRCL answered the queries & enlightened everyone about the project |
04 March 2016 |
Metro samvaad program was conducted in LAD college, North Ambazari Road on 4th March 2016. The students and faculty members actively participated in the discussion. Mr. Shirish Apte, DGM (PR) answered the queries on the topic. |
18 February 2016 |
In the presence of Hon. Dr. E. Sreedharan "Metro Man", NMRCL celebrated its 1st Foundation Day |
06 February 2016 |
NMRCL organised elocution Competition at Shri Ramdeobaba College of Engineering on 6th Feb,Present on occasion were S.M .Apte, DGM PR, NMRCL. Dr .Kapil Chandrayan,Principal Dr. Pande, HOD Dr. Shah and faculty members. |
21 January 2016 |
Metrosamvad at G.H.Raisoni College of Engineering, Hingna |
13 January 2016 |
Metrosamvad was held on 13th Jan 2016 at CIBMRD, Nagpur |
13 January 2016 |
Metrosamvad was held on 13th Jan 2016 at Gandhibagh Garden, Present on the occasion were Shri. Dayashankar Tiwari, Leader of ruling party in NMC House & Shri. Shirish Apte, DGM (PR) |
05 December 2015 |
MD of Nagpur Metro rail corporation Shri. Brijesh Dixit interacted with Vidarbha Economic Development Council members ,Nagpur |
27 November 2015 |
Nagpur Metro "Majhi metro" nailed it by winning 2nd prize for best exhibitor at "8th Urban Mobility India conference and expo 2015" Hon. MD Nagpur Metro Shri Brijesh Dixit received award from Babul Supriyo, Hon. Minister of State for Urban Development |
05 November 2015 |
Metrosamvad was held on 5th Nov at G.H.Raisoni, Shradha House, Present on occassion were Mr. Rajeev Chand CEO Raisoni Group |
31 October 2015 |
Metrosamvad was held on 31th Oct 2015 at Hanuman Mandir, Shankar Nagar |
30 October 2015 |
Metrosamvad was held on 30th Oct 2015 at Sugandh Mangal Karyalay, Dharampeth |
19 October 2015 |
Metrosamvad was held on 19th Oct 2015 at PWS College, Kampte. Present on occassion were Principal Gat Sir, Corporator Shri. Gautam Patil, Corporator Sau.Savitatai Sangole |
24 September 2015 |
Metrosamvad was held on 24th Sep on 8:00 PM at Shri. Santi Ganesh Utsav Mandal, Chitaroli Road. Present on occasion were Shri. Sanjay Chinchole. |
24 September 2015 |
Metrosamvad was held on 24th Sep on 9:00 AM at Gudhe College, Hingna Road. Present on occasion were corporators Shri. Prafulji Gudhe. |
18 September 2015 |
Metrosamvad was held on 18th Sep at at Devi Ahilya mandir, Dhantoli. Present on occasion were corporators Shri Sandipji Joshi and Dr.Safalta Ambatkar. |
16 September 2015 |
Metrosamvad was held on 16th Sep at Ajni Square. Present on occasion were Shri. Shiledar Senior Citizen and Corporator Shri. Gopal Bohore. |
16 September 2015 |
Three tier model (Surface road,Flyover& Metro rail) for Metro Construction between airport & Ajni Square released on 16th Sep 2015 |
11 September 2015 |
Government of India & Ministry of Finance, Department of Economic Affairs has come up with; “New Financing Instrument for large-scale infrastructure projects" namely “ODA Plus Loan”
Nagpur Metro Rail is the first project to be considered eligible for acquiring funds, under this instrument of external funding for 500 million Euro from KFW (German Bank) |
8 September 2015 |
Metrosamvad was held on 8th Sep at Chatrapati Square. Present on occasion were Corporator Smt.Usha Nishitkar. |
2 September 2015 |
Delegation from Ministry of Economy, Trade & Industry of Japan (METI) visited Nagpur for detailed study of Nagpur Metro Rail Project |
28 August 2015 |
Possession of 0.066 HR Land of MIDC land handed over to NMRCL. Cumulative Land acquired is 66.80 HR, i.e 76.43% of the Land required as per DPR |
26 August 2015 |
Possession of 0.047 HR land of Govt.Technical School handed over to NMRCL |
26 August 2015 |
Possession of 0.75 HR Land under MTDC handed over to NMRCL |
26 August 2015 |
Possession of 0.22 HR Land of Patwardhan high School handed over to NMRCL |
18 August 2015 |
Nagpur Metro Rail Board Of Directors meeting |
17 August 2015 |
Loksamvad/Metrosamvad at Hanuman Mandir Ujwal Nagar |
14 August 2015 |
Review Meeting with Hon. Shri DEVENDRA FADNAVIS (Chief Minister Of Maharashtra) at Mumbai |
4 August 2015 |
Possession of 0.25 HR Land at Morris College T point handed over to NMRCL |
4 August 2015 |
Possession of 1.99 HR Land at Morris College ground handed over to NMRCL |
8 July 2015 |
European Investment Bank from Luxembourg visited Nagpur Metro Rail Project |
2 June 2015 |
Delegation from KFW(German Bank) visited Nagpur for detailed study of Nagpur Metro Rail Project |
31 May 2015 |
Karyarambha Ceremony of Nagpur Metro Rail Project at Khapri in presence of honourable Shri. DEVENDRA FADNAVIS (Chief Minister Of Maharashtra), Shri. NITIN GADKARI (Union Minister Of Urban Transport and Shipping). |
16 May 2015 |
Geotechnical investigation of the entire alignment has start from 16th may 2015. It will involve
-investigation of soil and rock below ground, so that the same can be used for the foundation of the metro.
-cost involves lab testing of the samples collected, etc.
The said work will be completed in 2 months |
6 May 2015 |
"Detailed Geotechnical Investigation and report for Nagpur Metro Rail System in Nagpur" Tender is open |
30 Apr 2015 |
"Selection Of Project Management Consultant for Utilities shifting for Nagpur Metro Rail Project" Tender will be opened on 15th May 2015 |
18 Apr 2015 |
"Detailed Geotechnical Investigation and report for Nagpur Metro Rail System in Nagpur" Tender will be opened on 6th May 2015 |
17 Apr 2015 |
Tender will be opened on 18th May 2015-“CONSTRUCTION OF BRIDGES (INCLUDING RAIL-OVER-BRIDGE OVER CONCOR SIDING AT KHAPRI). " |
1 Apr 2015 |
DMRC, RITES are appointed as interim consultant for Nagpur Metro Rail Project.
DMRC
- Bid Process Management for Selection of General Consultant
- Preparation of Schedule of Dimensions.
- Preparation of Design Basis Report.
RITES
Review of DPR in regard to traction type, coach width, platform length, and train length and critical review of alignment particularly as below but not restricted to:
a) Interchange station building at Munje Chowk with parking integration.
b) Chatrapati Nagar Square with station
c) Alignment between IGGMC & railway station on East-West corridor
d) Cotton Market Square to Anand talkies
e) Prajapati Nagar Square (junction of Ring Road & Bhandara Road)
f) CONCOR siding in MIHAN.
Preparation of bid document & bid process management for appointment of execution agency for priority section between Airport – Khapri MIHAN (excluding depot)
Preparation of bid documents for design & build viaduct portion of first elevated reach between Airport and Sitaburdi interchange (Munje Chawk).
Provide GFC drawings for the priority section
Preparation of bid document & bid process management for appointment of DDC (Detailed design Consultant including structural & architectural both) for stations including appointment of Architect for the interchange station (Sitaburdi).
|
27 March 2015 |
French Delegation visited Nagpur for detailed study of Nagpur Metro Rail Project |
22 Feb 2015 |
Agreement with DMRC for preparation of DPR |
18 Feb 2015 |
Incorporation Of Nagpur Metro Rail Corporation Limited |
12 Feb 2015 |
MADC transfered 37 ha land to NMRCL that includes land required for Depo |
11 Feb 2015 |
Possession of 37.40 HR land out of 45.89 HR in MADC handed over to NMRCL |
21 Aug 2014 |
Approval of GoI to the project |
11 Feb 2014 |
In Principle approval by MoUD, GoI |
30 Jan 2014 |
Draft DPR approved by the State Government |
May 2013 |
Traffic Survey |