Land Acquisition

Total Land requirement is 86.83 Ha
Possession received of Land 79.81 Ha
% of Total Land 91.91%
Action for acquiring the remaining land is in progress.

List of Government Land in possession of NMRCL

Name Of Department Mouza Survey No. City Survey No. Area Of Land in H.R/Sq.mts Purpose Date Of Possession
S.R.P.F Nildoh 18 - 260700 Sq.Mts Car depot 04/08/2015
Morris College T. Point Sitabuldi 302 1848 2535.77 Sq.Mts RS 04/08/2015
Morris College Ground Dhantoli 98,99,100,101 9 19889.9 Sq.Mts Parking 04/08/2015
Pathwardhan High School Sitabuldi 303 1847 2252.63 Sq.Mts Station 04/08/2015
MTDC Sitabuldi 169 1864 7495.00 Sq.Mts Parking 04/08/2015
Govt. Technical School Nagpur 374 101 469.67 Sq.Mts RS 04/08/2015
MIDC Digdoh(Devi) 31,32 - 290.20 Sq.Mts Station 04/08/2015
MIDC Digdoh(Devi) 05 - 1095.614Sq.Mts Station 22/11/2016
Pathwardhan High School (Open Space) Sitabuldi 303 1847 1414.124Sq.Mts Station / Resettlement 04/02/2016
Shahid Kakde Bhankheda 82 495 314.936 Sq.Mts Running Section 16/05/2016
Mayo Hospital Bhankheda 82 1397 713.870 Sq.Mts E/DGF at Running section 19/05/2016
Prajapati Nagar Pardi 45/1, 47, 51, 63/1, 64, 65, 66,74/2,75 160 2749.955 Sq.Mts Entry-Exit Parking 20/07/2016
Ujjwal Nagar Ground Somalwada 120/1 380 5642.48 Sq.Mts Parking 20/07/2016
Metro Bhavan Lendra 225 1261 6359.84 Sq.Mts Metro Bhavan 06/08/2016
Ambazari Lake View Ambazari 3,4,9/1, 42/2, 2581 3353.093 Sq.Mts Station 04/10/2016
Patwardhan High school Sitabuldi - - 608.231 Sq. Mts Station 23/12/2016
Morris College T Point Sitabuldi - - 2697.658 Sq.Mts - 23/12/2016
World Bank Project (PWD) - - - 3320.43 Sq.Mts - -

Land Acquisition for NMRCL

Name Of Department Land Required as per DPR in HR Collecting Order for handling over advance possession H.R Physical Possession Taken H.R Remarks
State Government 33.77 32.02 32.58 95.05%
MIDC 0.14 - 0.14 100%
Government Of India 2.64 - -  
NIT 3.36 - 1.92 57.31%
NMC 1.09 - 0.9 97.28%
MADC 43.45 - 40.95 94.27%
MIL 1.48 - 1.48 100%
Private 2.09 - 1.50 72.10%
Total 86.83 32.03 79.81 91.91%

Physical progress

1.   Consultant :

1.DMRC & RITES has been appointed as Interim Consultants.
2. ERNST & YOUNG LLP has been appointed as Consultant for "Smart Card and Automatic Fare Collection System".
3. AFC INDIA LTD. & CENTRE FOR ENVIRONMENT RESEARCH & DEVELOPMENT has been appointed as Consultant for "Social Impact Assessment Studies"
4. L&T INFRASTRUCTURE ENGINEERING LTD. & M/S RAJENDRAN ASSOCIATES have been appointed as Consultants for Detailed Design of 9 Stations on N-S Corridor.
5.Consortium of Systra, Egis, AECOM & RITES have been appointed as consultants for GC & DDC
6. Aurionpro have been appointed as consultants for implementation of IT platform involving ERP and 5D BIM.
7. Consortium of Enia Architects, Mahendrarai Consultants & Workspace Consulting been appointed as consultants for Planning, architectural design of Sitaburdi Interchange, Zero Mile station and TTMC at Sitaburdi.

2.    Tenders Awarded :

1. CONSTRUCTION OF FOUR LANE ROAD FROM TCI WAREHOUSE TO KHAPRI STATION, PROVIDING RCC DRAIN, CANVAS CONCRETING AT GRADE SECTION WITHIN METRO CORRIDOR NEAR MIHAN ROB 2. SHIFTING AND RELAYING OF EXISTING SEWER LINES INFRINGING WITH METRO CORRIDOR WITHIN NMC LIMIT.
3. PROVIDING SERVICES OF QUICK RESPONSE TEAM (QRT) CUM RESCUE TEAM FOR MAHA- METRO (NAGPUR METRO RAIL PROJECT) FOR A PERIOD OF TWO YEARS ON OUT SOURCE BASIS
4. SUPPLY , INSTALLATION, TESTING AND COMMISSIONING OF ONE ) 16 SPLIT HEAD B TAMPING MACHINE FOR TAMPING OF BALLASTED TRACK LAID ON MAIN LINE AND IN THE TWO MAINTENANCE DEPOTS. (SECOND CALL)
5. SHIFTING OF LT, HT, O/H LINE, CROSSING AND PROVIDING LT, HT, U/G CABLE TRANSFORMERS, RMU`s, CABLES FROM KAMGAR NAGAR (CH.0500) TO TEKA NAKA (CH.1175) FOR NAGPUR METRO RAIL PROJECT ON N-S CORRIDOR REACH-2.
6. SHIFTING OF LT, HT, O/H LINE, CROSSING AND PROVIDING LT, HT, U/G CABLE TRANSFORMERS, RMU`S, CABLES FROM CHOUKS COLONY (CH.1750) TO INDORA CHOWK (CH.2275) FOR NAGPUR METRO RAIL PROJECT ON N-S CORRIDOR REACH-2.
7. SHIFTING OF LT, HT, O/H LINE CROSSING AND PROVIDING LT, HT , U/G CABLE TRANSFORMERS RMU`S CABLES FROM INDORA CHOWK (CH.2275) TO RAILWAY ROB (CH.4000) FOR NAGPUR METRO RAIL PROJECT ON N-S CORRIDOR REACH-2
8. HIRING OF VEHICLES (TAXIES) FOR OFFICIALS OF MAHARASHTRA METRO RAIL CORPORATION LIMITED (NAGPUR METRO RAIL PROJECT) - (SECOND CALL)

3.    Work In Progress :

Reach - I

A) Viaduct Portion -

* Pile foundation of 99% completed in viaduct portion.
* Pile Cap about 98% completed in viaduct portion.
* Piers about 96% completed in viaduct portion.
* Pier caps about 90% completed in viaduct portion.
* Metro Span about 61% completed in viaduct portion.
* Metro Segment casting about 82% completed in viaduct portion.

B) NHAI Portion -

* Pile foundation about 98% completed in viaduct portion.

C) Stations Portion -

* Total 7 No. of stations work under progress in Reach I.
* 94% Pile foundation is completed in Stations portion.
* 56% Pile Caps is completed in Stations portion.
* 68% Rectangular Girders is completed in Stations portion.
* 65% I Girders is completed in Stations portion.

D) Manish Nagar Portion -

* 65% Open foundation is completed in Manish Nagar portion.
* 71% Piers is completed in manish Nagar portion.

Reach - II

1. LAND ACQUISITION -

In Progress

2. STATION PORTION -

* Work has been awarded to M/s ITD Cementation India Ltd. and the work is in progress in all 6 nos. stations in Reach-2
* Pile foundation of 86% completed in central viaduct portion.
* Pile Cap about 73% completed in central viaduct portion.
* Pier about 64% completed in central viaduct portion.
* Cross Beams at NHAI flyover level is in progress
* Casting of I-Girders of about 20% completed.
* Entry/Exit Structure foundation works on off road are in progress at Automotive Square Station and Nari Road Station
* Secant piling work and Excavation work is completed. The raft foundation work and columns works is in progress at Gaddigodam Station off road area.
* Secant piling work is completed in Kasturchand Park Station off road area and excavation about 81% completed.

3. VIADUCT PORTION -

* Work has been awarded to M/s AFCONS Infrastructure Ltd. and the work is in progress from Automotive Square to Sitabuldi.
* Pile foundation of 33% completed in viaduct portion.
* Pile Cap and Pier work is in progress.
* Metro Viaduct Segment and NHAI Flyover Segment Casting has been started and in progress.
* For Launching of Metro viaduct Segments near Zero Mile Station, the mobilization of launching materials (GSS - Ground Support System) is started.
* Fabrication of Launching Girder for Double-Decker Launching work is in progress.

4. HIGHLIGHTS -

* The piling work has been started at Munje Chowk area in between variety square and sitabuldi section in viaduct portion.
* The barricading work for piling work of central viaduct portion of Gaddigodam station has been started.

1. "Rise of Wings"Cantilever wings (7m wide 4Lane) were launched by MahaMetro on either side of the central spine of Nagpur Metros 3.41 km double-decker viaduct which is being built on Wardha Road as part of the 22.293 km Line-1 between Automotive Square and Metro City.
2. Airport Metro Station - 1st Elevated Station, Airport Station, concourse slab,Massive Task Execution Started.
3. First cross beam at NHAI level at Automotive square station has been cast.
4. Launching Girder erection completed and ready for segment erection work , area Chitaroli to Agrasen Chowk.
5. Track Linking Work in the Hingna Corridor. Linking work between Lokmanya Nagar and Subhash Nagar has been initiated by placing `Flash Butt Welding Machine’ on viaduct.
6. Work in Progress at Automotive Square to Indora Chowk
7. Subhas nagar station entry structure, roof top slab in progress .
8. First Pier concrete P-230 started at Zero Mile on Reach 2 of Sitabuldi to Automotive square.
9. Piling Activities going on for Viaduct North – South Corridor. P 51-48 pier Re-bar fixing work in progress on the Nari Road.
10. Spine supporting Double Decker bridge @ Wardha raod
11. Yes LGA auto launching completed between P113 to P114

4.    Tenders Invited :

1. DEVELOPMENT AND OPERATIONS OF PART OF LAND AT KH. NO. 98, 99, 100, 101 AT MZ. DHANTOLI NEAR SITABURDI INTERCHANGE STATION OF NAGPUR METRO RAIL PROJECT ON PUBLIC PRIVATE PARTNERSHIP (DBFOT) BASIS
2. DESIGN, MANUFACTURE, SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF PLATFORM SCREEN GATES AND PLATFORM SCREEN DOORS SYSTEM FOR NAGPUR METRO RAIL PROJECT.
3. ANNUAL MAINTENANCE OF 5000 TRESS AT LITTLE WOOD PLANTATION AT AMBAZARI FOR THE YEAR 2018-2019

5.    Architectural Competition :

1. Consortium of Enia Architects, Mahendrarai Consultants & Workspace Consulting been appointed as consultants for Planning, architectural design of Sitaburdi Interchange, Zero Mile station and TTMC at Sitaburdi.

Financial Progress

Sr No. Funding Agency Amount as per sanction (Rs. in Crs) Budgetary allocation in FY 2015-16 including Subordinate Debt (Rs. in Crs) Amount
(Rs.in Crs).

1

GoI

1555

603

629.62**

2

GoM

1736*

176.5

3

NIT (ULB contribution)

 434

40.00

4

NMC (ULB contribution)

 434

0.00

5

External funding

4521

0.00

Total

8680

891.5

* includes Rs 181 Crs State taxes
** 1) Rs.479.4 Crs has been the payment made towards Land Acquisition
2) Expenses upto 31st May 2016

Organizational Progress

Particulars Nagpur Metro Pune Metro Total Count of MAHA-Metro
1. Current Strength of the Organization The current organizational strength is 247 employees The current organizational strength is 80 employees 327
2. Head Count of people Outsourced Currently MAHA-Metro, Nagpur, employees are 105 people who are working in the pay rolls of placement agencies Currently MAHA-Metro, Pune, employees are 22 people who are working in the pay rolls of placement agencies 127
3. Head Count of people working under Consultants A total of 07 people are working for MAHA-Metro, Nagpur, under the rolls of Consultants appointed by MAHA-Metro Nil 07
4. Total Head Count Total number of employees working for MAHA-Metro, Nagpur is currently 359 people Total number of employees working for MAHA-Metro, Pune is currently 102 people 461

Milestone

Date Event

19 May 2018

Foundation Work (Pile Cap Reinforcement) at Pier Location P244 between Munje Chowk to Variety Chowk for Viaduct Portion in Reach - 2. Staging Work for Fixing Pier Reinforcement at Pier Location P245.

17 May 2018

Metro Samvad & Skating Rally Held at Central Avenue, Gandhibag

15 May 2018

Sitabuldi to Automotive Square corridor -
Construction of Elevated Viaduct in Reach-2 between Pier Location P231/P232 at Sitabuldi - Assembly of Ground Support Trestle (Underslung) by Hydraulic Crane for Span Erection

04 May 2018

Nagpur Metro Rail Project has come up with yet another first in the city with a specially designed Hash Tag crafted to showcase the vibrancy associated with the Project. Hon’ble MD, MahaMetro Shri. Brijesh Dixit did the honors of the inauguration.

03 May 2018

A delegation of KfW – the German government-owned development bank financing Nagpur Metro project – visited to Maha Metro

26 April 2018

Pile Cap Exacavation & Shoring Work is in progress at P245 between Variety Chowk and Munje Chowk Viaduct Portion.

25 April 2018

Hingna Casting Yard
101 Nos. out of 514 Nos. I-Girder Casting Completed for Station Portion in Reach-2 at Hingana Casting Yard.

21 April 2018

First Pre-Launch ride with Under privileged People and Celebrity Marathi Actor Sachin Pilgaonkar & Swapnil Joshi

21 April 2018

Automotive Corridor Viaduct work
1st Pier Cap of Metro Viaduct Level at Pier Location P230 Near Sitabuldi cast on 20.04.2018 in Reach-2

19 April 2018

Airport Metro Station Update
1st elevated station casting of 1st part of concourse level loading & unloading slab successfully completed.

18 April 2018

CMRS Inspection Over, Decks Clear for Joy Ride
The second and final inspection of Maha Metro Nagpur project was undertaken by a Commissioner of Metro Rail Safety (CMRS)

17 April 2018

Segment erection work from Chitaroli Chowk to Agrasen Chowk in progress
15 number of span erection completed (in segments 167 segment erected)
Length of segment - 3mts .
Width of segment -8.5 mts

16 April 2018

Maha Metro, Nagpur has been Conferred with the prestigious SAP ACE Award. The award was presented at a glittering function held at Parel, Mumbai. The award was Conferred on Nagpur Metro for its pioneering work in the field of 5D BIM.

12 April 2018

Achievement - 501 numbers Out of 1630 Piles Completed for Viaduct Section near Kadbi Chowk

11 April 2018

became most followed FB page among all the Metro Rail projects in India.

09 April 2018

Maha Metro officials organised Metro Samwad at Gurudwara Area on Kamathi Road on 09th April 2018

06 April 2018

Total 60 "I" girder erected at Institution Of Engineers Metro Station. First concourse deck slab between sp1-sp2 casting completed Successfully on 22nd march 2018

30 March 2018

Metro Samwad program being conducted in Anjuman College of Engineering and Technology, Mangalwari bazaar road, Sadar, Nagpur, The students and faculty members actively participated in the discussion.

28 March 2018

Pune Media as study tour visited to Nagpur Metro Rail Project

27 March 2018

The work of ROB is visible over the ground now. U-Trough work for Manish Nagar is 80% completed and the procurement works for U-trough accessories is under procurement.

23 March 2018

An amazing "Metro Samwad" of Metro Friends and Fans was conducted at Little Wood, Hingna road on Friday. Nagpur Metro`s ongoing construction activities on the stretch of Sitabuldi to Lokmanya Nagar.

22 March 2018

New Airport Metro Station - 90% ground level work is done at At-Grade area of the priority section

17 March 2018

MSRDC Ramjhula - as per scope 5 no span casting completed, ramp retaining wall casting completed ramp portion filling work and crash barrier work is in progress

17 March 2018

MSRDC Ramjhula - as per scope 5 no span casting completed, ramp retaining wall casting completed ramp portion filling work and crash barrier work is in progress

06 March 2018

Cantilever wings (7m wide 4Lane) were launched by MahaMetro on either side of the central spine of Nagpur Metro`s 3.41 km double-decker viaduct which is being built on Wardha Road as part of the 22.293 km Line-1 between Automotive Square and Metro City.

22 February 2018

Maha Metro Starts Welding of Rails in Hingna Corridor Reach 3.

19 February 2018

MAHA METRO participated in the Magnetic Maharashtra Convergence 2018.

17 February 2018

Maha Metro Celebrate 3rd Foundation Day.

8 February 2018

First Pier concrete P-230 started at Zero Mile on Reach 2 of Sitabuldi to Automotive square Corridor by M/S Afcons.

5 February 2018

National Safety Week was observed in Maha Metro.

3 February 2018

Maha-Metro conducted a meeting and open discussion with Stakeholders.

19 January 2018

Nagpur Metro was organised a Metro Samvad at Shankarlal Jalan Foundation, Bhandara road.

18 January 2017

KFW Team Visits Nagpur Metro Project.

17 January 2018

CMRS Team Visited Maha Metro Nagpur Project and Inspects Facilities

15 January 2018

Maha Metro Celebrated Road Safety Week awareness program from 08th to 14th Jan 2018 with staff, workforce, and local public...

13 January 2018

Maha Metro Nagpur launches first TETRA Tower

30 December 2017

RDSO approval for the re-designed tubular portal by Maha Metro

20 December 2017

Additional Metro Rail Coaches Arrive in Nagpur

18 December 2017

400k Likes is achieved on Nagpur Metro facebook page

06 December 2017

RDSO has issued the speed certificate for operation of trains between Khapri and Airport South metro stations.

05 December 2017

Nagpur Metrop is organised Metro Samvad at Sitabuldi on 05 Dec 2017

30 November 2017

Stage is set for the commercial run of Nagpur Metro on a segment with the arrival of Automatic Fare Collection (AFC) gates. To be installed at the three priority stations of Airport South, New Airport and Khapri initially - the AFC gates would revolutionize travel in Nagpur. A demonstration of AFC gates was conducted

27 November 2017

Pukeshwar and Geeta watgure emerged as the fastest athletes in the 21 km MahaMetro Nagpur Marathon on Sunday, 26th Nov. The prizes all the four races were distributed by World Boxing Champion MC Mary Kom. Dr. Brijesh Dixit, Managing Directer, MahaMetro Presided over the ceremony.

24 November 2017

MahaMetro has completed the casting of 1000 segments as a part of Reach-3. The East-West corridor will have 10 stations and 10.2 Km Viaduct route operating in between Jhansi Rani Square to Lokmanya Nagar. “M/s AFCONS Infrastructure Ltd.” and Team are working on this site.

22 November 2017

Hon. Brijesh Dikshit, MD Maha Metro was the key speaker in joint venture of Unnati Foundation and Chhatra Jagruti on 'Maha Metro : yesterday, Today and Tomorrow' mahaSanwad held at Dhanwate sabhagruh, shankar nagar on tuesday. Dr. Dixit being honoured for getting PhD. in Economics of Safety on Indian Railway by Organisers.

16 November 2017

Nagpur Metro was organised a Metro Samvad at Vyapari Association, Indora Square

07 November 2017

Maha Metro has been chosen for the central urban development ministrys award for the countrys best urban mobility project.

30 October 2017

Nagpur Metro has executed concrete pour of 2200 Cu. Mtr for administrative building at Mihan Depot

16 October 2017

Maha Metro erected its 4th and last Steel Girder at Ramzula Section

30 September 2017

Flag off the trial run of Majhi Metro and the launch a Smart Mobility card - Maha Card, at the hands of CM Devendra Fadnavis and Union Minister Nitin Gadkari

24 September 2017

First steel girder erection completed out of 4 steel girders above Ramjhula

18 September 2017

A Final test done by Nagpur Metro for Trial Run. Maha Metro successfully Run Buland (The Electrical shunting vehicle utilized for Track testing) between Mihan Depot to Khapari Metro station.

07th September 2017

A team of "Research Design and Standard Organization (RDSO)" and Maha-Metro did a joint inspection of At Grade Section

05th September 2017

On the auspicious occasion of Anant Chaturdashi, Shri Brijesh Dixit,Hon MD.Maha Metro performed bhumipujan of Eco Park at Mihan

04th September 2017

Shri Brijesh Dixit, Honble MD, MahaMetro did an inspection by Rail Trolley of the track on which coaches will be seen running

20th August 2017

Maha-Metro Rail Corporation is executing the biggest concrete pour at Zero Mile Station.

14th August 2017

A Traction Substation (TSS) was inaugurated by Hon. Brijesh Dixit, Managing Director Maha Metro.

02nd August 2017

Three metro bogies arrived in the city for trial run.

10th July 2017

'Maha-Metro BIM Advancement Academy' started at Nagpur under the stewardship of Mr. Brijesh Dixit, MD Maha-Metro.

08th June 2017

Bhumi Pujan of Reach conducted 4 at the hands of Shri Brijesh Dixit, Hon. Managing Director, MahaMetro.

01st June 2017

Head hardened rail for Nagpur Metro rail project arrived from Russia.

04th May 2017

Nagpur Metro Facebook Page Received 3, 00,000 likes

01st May 2017

Bhumi Pujan of Signaling System was performed at Khapari Station at the hands of Shri Brijesh Dixit, Hon. Managing Director, MahaMetro.

19th April 2017

Sahyog Kendra Started in front of Yashwant stadium.

13th April 2017

First Pier of Jhansi Rani square to Lokmanya nagar reach of East-west Corridor erected.

10th April 2017

Shri Brijesh Dixit, MD, MAHA Metro inaugurated the testing facility and laboratory, which is a Joint Venture between MAHA-METRO and Bureau Veritas, at Nagpur.

07th April 2017

Nagpur Metro participated in "Smart City Summit 2017" conducted at Nagpur.

24th March 2017

The Work contract for the 7.657 Km stretch between Munje chowk to Projatpati Nagar is awarded to M/s ITD Cementation India Ltd.

15th March 2017

Work of Nagpur Metro starts at Munje Sq.

18th February 2017

Honble MD, Shri Brijesh Dixit, inaugurated "Metro Mahiti Kendra" at LIC sqaure.

10th February 2017

The tender for Roof Top Solar PV Project (from stage of Designing to Testing & Commissioning and including Comprehensive Maintenance) in Metro Bhawan - the corporate office building of Nagpur Metro, has been awarded to consortium of M/S. Option Sales Pvt Ltd,M/S Welspun Energy Pvt Ltd & M/S Hygrid Solar Pvt Ltd.

01st February 2017

The work of Signaling and Train Control of Nagpur Metro is awarded to Consortium of M/s SIEMENS Ltd India & Siemens Rail Automation, Spain.

31st January 2017

The Raft Foundation of Airport Station Ancillary Building has been laid.

27th January 2017

Nagpur Metros segment erection work at Pride Hotel junction has been completed.

24th January 2017

Maharashtra Metro Rail Corporation Limited finally and formally comes into existence by reconstitution of Nagpur Metro Rail Corporation Limited.

18th January 2017

LOI for Design, manufacture, Supply, Installation, testing and commissioning of Signalling and Train Control System awarded to M/S. Siemens Roll Automation, S.A.U.

14th January 2017

Nagpur Metro Facebook Page Received 2, 50,000 likes

12th January 2017

The rails for at-grade section arrived at Nagpur.

12th January 2017

Shri Brijesh Dixit, MD, NMRCL inaugurated Nagpur Metro's stall at Comp-Ex 2017. The stall highlights were IT applications adopted by NMRCL.

28th December 2016

LOI for Construction of NHAI Flyover originating from Ujjwal Nagar on the North-South corridor of Nagpur Metro Rail Project to Manish Nagar in Nagpur awarded to M/s NCC Ltd

19th December 2016

Bhoomipujan For Construction Of MIHAN Rolling Stock Depot For N-S Corridor Performed On 19/12/2016.

09th December 2016

LOI for Design, Engineering, Manufacture, Supply, Storage Civil work, Erection, Testing & Commissioning of the Rooftop Solar PV project including O&M at Metro Bhawan awarded to M/s. Option Sales Pvt Ltd, M/s Welspun Energy Pvt Ltd & M/s Hygrid Solar Pvt Ltd.

1st December 2016

Bhoomipujan for construction of Reach 3 Viaduct between Jhansi Rani Sq and Lokmanya Nagar performed on 01/12/2016

30th November 2016

LoI for Construction of Metro Train Depot at MIHAN (N-S corridor) & Hingna (E-W Corridor) including Civil & E&M Works awarded to M/s Pratibha CSL Sudhir Constructions JV

17th November 2016

Funding Agreement of 130 Million Euros for NMRCL project signed betweeb DEA and AFD France

28th October 2016

LOI for Design and Construction of viaduct on reach-3 between Jhansi Rani Square to Lokmanya Nagar Stations on E-W corridor of Nagpur Metro Project awarded to AFCONS infrastructure ltd

15th October 2016

LoA for Manufacture and Supply of Passenger Rolling Stock for Nagpur Metro Project signed between NMRCL and CRRC, China , in the presence of Hon. Union Minister For Surface Transport and Shipping - Shri Nitin Gadkari, Hon. Chief Minister of Maharashtra - Shri. Devendra Fadnavis, Hon. MD - NMRCL - Shri. Brijesh Dixit and other dignitaries.

06th October 2016

Bhoomipujan of Dharampeth(Ambazari) Metro station was performed by Hon. M D of NMRCL

20th September 2016

LoI for construction of 10 Nos Elevated Metro Stations (excluding Via-duct) on the E-W Corridor in Reach-3 awarded to ITD Cementation

02nd September 2016

Bhoomipujan of New Airport metro Station performed by Hon. MD of NMRCL

17th August 2016

First Segment of Via-duct Launch completed on N-S Corridor between Cargo Terminus Road and Pride Hotel Square

12th August 2016

Bhoomipujan of Khapri metro station performed by Hon. MD of NMRCL

27th July 2016

MoU With Bureau Veritas India To Set Up And Jointly Run World Class NMRCL-BVIL Laboratory For Testing Of Material Used In Construction And Other Civil Works.

24th July 2016

MOU Signed Between NMRCL & DRDO

23th July 2016

Metrosamvad- A Public Interaction Program Was Organised At Wainganga College Of Engineering . Dignitaries Present On The Occasion Were Vice Principal Surbhi Shrivastava , CEO Of College Dr. Rohit Manjule, HR & Corporate Relation Mr. Pravin Wat

21st July 2016

Construction of 7 elevated metro stations and 3 At grade stations at the N-S corridor awarded to IL&FS ECC Ltd

1st July 2016

Tree Plantation Program at Vasudev Nagar in Ambazari Tank submergence area.

29th June 2016

Team Metro organised Metrosamvad with Taffic Police Department at DCP Traffic Office, Present on occasion were DGM (PR) NMRCL Shri. Shrish Apte , Security Advisor NMRCL Shri. Arvind Giri

27th Jun 2016

As a symbol of Solar initiative of Nagpur Metro, a Battery Operated Vehicle named SOLARPULSE ONE chargeable on Solar power launched at the hands of, Honourable Chief Minister of Maharashtra, Shri. Devendraji Fadnavis.

11th June 2016

NMRCL organised Metrosamvad at Datta Mandir Parsodi, Dakshin Paschim Nagpur Jeshta Nagrik Sangh. Present were President Sri. Kate, Shri. S.M. Apte DGM (PR) & other office bearers.

31st May 2016

NMRCL organised Metrosamvad at MIHAN

27th May 2016

NMRCL & Baljagat jointly organised Metrosamvad & Chitrakala Spardha

25th May 2016

NMRCL conducted Metrosamvad at VIA on 25th May 2016. Present on the occasion were Mr. Atul Pande,President VIA ; Mr. Rohit Agarwal ,Secretary VIA; Mr. Sunil Mathur, Director (Rolling Stock) NMRCL; Mr. S. M. Apte, DGM (PR)NMRCL & Mr. Vinod Kumar Nagar JGM (Stores) NMRCL.

14th May 2016

Hon. Brijesh Dixit M.D NMRCL inaugurated sample collection center for Quality Control Laboratory

20th April 2016

The first Pier of elevated corridor is constructed on Wardha Road. The pier is based on Pile foundation with 4 no. of piles having diameter of 1.2mtr each. On the top of Pile foundation is Pile cap of Size 5.7x5.7. The Pier size is 1.5 mtr x2.00 mtr. & Height of Pier is nearly 8.5 mtr. The grade of concrete is M 60.

10 April 2016

The Project agreement with Kfw was signed on 10th April 2016 by Hon. Managing Director, Mr.Brijesh Dixit & Director, Kfw India,Mr. Peter Hilliges

06th April 2016

NMRCL conducted Metrosamvad at Eastern Sports Club

01st April 2016

Agreement Signed between DEA & KFW Bank of Rs 3750 Cr for Nagpur Metro Rail at Delhi

28th March 2016

NMRCL conducted "Metrosamvad"- A Public Interaction Program at G S College, Nagpur.Happy to received such a good response from students & Faculty members.They were so curious & interactive. S.M. Apte, D.G.M (P.R), NMRCL answered the queries & enlightened everyone about the project

04th March 2016

Metro samvaad program was conducted in LAD college, North Ambazari Road on 4th March 2016. The students and faculty members actively participated in the discussion. Mr. Shirish Apte, DGM (PR) answered the queries on the topic.

18th Feb 2016

In the presence of Hon. Dr. E. Sreedharan "Metro Man", NMRCL celebrated its 1st Foundation Day

06th February 2016

NMRCL organised elocution Competition at Shri Ramdeobaba College of Engineering on 6th Feb,Present on occasion were S.M .Apte, DGM PR, NMRCL. Dr .Kapil Chandrayan,Principal Dr. Pande, HOD Dr. Shah and faculty members.

21st January 2016

Metrosamvad at G.H.Raisoni College of Engineering, Hingna

13th January 2016

Metrosamvad was held on 13th Jan 2016 at CIBMRD, Nagpur

13th January 2016

Metrosamvad was held on 13th Jan 2016 at Gandhibagh Garden, Present on the occasion were Shri. Dayashankar Tiwari, Leader of ruling party in NMC House & Shri. Shirish Apte, DGM (PR)

05th December 2015

MD of Nagpur Metro rail corporation Shri. Brijesh Dixit interacted with Vidarbha Economic Development Council members ,Nagpur

27th November 2015

Nagpur Metro "Majhi metro" nailed it by winning 2nd prize for best exhibitor at "8th Urban Mobility India conference and expo 2015" Hon. MD Nagpur Metro Shri Brijesh Dixit received award from Babul Supriyo, Hon. Minister of State for Urban Development

05th November 2015

Metrosamvad was held on 5th Nov at G.H.Raisoni, Shradha House, Present on occassion were Mr. Rajeev Chand CEO Raisoni Group

31th October 2015

Metrosamvad was held on 31th Oct 2015 at Hanuman Mandir, Shankar Nagar

30th October 2015

Metrosamvad was held on 30th Oct 2015 at Sugandh Mangal Karyalay, Dharampeth

19th October 2015

Metrosamvad was held on 19th Oct 2015 at PWS College, Kampte. Present on occassion were Principal Gat Sir, Corporator Shri. Gautam Patil, Corporator Sau.Savitatai Sangole

24th September 2015

Metrosamvad was held on 24th Sep on 8:00 PM at Shri. Santi Ganesh Utsav Mandal, Chitaroli Road. Present on occasion were Shri. Sanjay Chinchole.

24th September 2015

Metrosamvad was held on 24th Sep on 9:00 AM at Gudhe College, Hingna Road. Present on occasion were corporators Shri. Prafulji Gudhe.

18th September 2015

Metrosamvad was held on 18th Sep at at Devi Ahilya mandir, Dhantoli. Present on occasion were corporators Shri Sandipji Joshi and Dr.Safalta Ambatkar.

16th September 2015

Metrosamvad was held on 16th Sep at Ajni Square. Present on occasion were Shri. Shiledar Senior Citizen and Corporator Shri. Gopal Bohore.

16th September 2015

Three tier model (Surface road,Flyover& Metro rail) for Metro Construction between airport & Ajni Square released on 16th Sep 2015

11th September 2015

Government of India & Ministry of Finance, Department of Economic Affairs has come up with; “New Financing Instrument for large-scale infrastructure projects" namely “ODA Plus Loan”
Nagpur Metro Rail is the first project to be considered eligible for acquiring funds, under this instrument of external funding for 500 million Euro from KFW (German Bank)

8th September 2015

Metrosamvad was held on 8th Sep at Chatrapati Square. Present on occasion were Corporator Smt.Usha Nishitkar.

2nd September 2015

Delegation from Ministry of Economy, Trade & Industry of Japan (METI) visited Nagpur for detailed study of Nagpur Metro Rail Project

28th August 2015

Possession of 0.066 HR Land of MIDC land handed over to NMRCL. Cumulative Land acquired is 66.80 HR, i.e 76.43% of the Land required as per DPR

26th August 2015

Possession of 0.047 HR land of Govt.Technical School handed over to NMRCL

26th August 2015

Possession of 0.75 HR Land under MTDC handed over to NMRCL

26th August 2015

Possession of 0.22 HR Land of Patwardhan high School handed over to NMRCL

18th August 2015

Nagpur Metro Rail Board Of Directors meeting

17th August 2015

Loksamvad/Metrosamvad at Hanuman Mandir Ujwal Nagar

14th August 2015

Review Meeting with Hon. Shri DEVENDRA FADNAVIS (Chief Minister Of Maharashtra) at Mumbai

4th August 2015

Possession of 0.25 HR Land at Morris College T point handed over to NMRCL

4th August 2015

Possession of 1.99 HR Land at Morris College ground handed over to NMRCL

8th July 2015

European Investment Bank from Luxembourg visited Nagpur Metro Rail Project

2nd June 2015

Delegation from KFW(German Bank) visited Nagpur for detailed study of Nagpur Metro Rail Project

31st May 2015

Karyarambha Ceremony of Nagpur Metro Rail Project at Khapri in presence of honourable Shri. DEVENDRA FADNAVIS (Chief Minister Of Maharashtra), Shri. NITIN GADKARI (Union Minister Of Urban Transport and Shipping).

16th May 2015

Geotechnical investigation of the entire alignment has start from 16th may 2015. It will involve

-investigation of soil and rock below ground, so that the same can be used for the foundation of the metro.

-cost involves lab testing of the samples collected, etc.

The said work will be completed in 2 months

6th May 2015

"Detailed Geotechnical Investigation and report for Nagpur Metro Rail System in Nagpur" Tender is open

30th Apr 2015

"Selection Of Project Management Consultant for Utilities shifting for Nagpur Metro Rail Project" Tender will be opened on 15th May 2015

18th Apr 2015

"Detailed Geotechnical Investigation and report for Nagpur Metro Rail System in Nagpur" Tender will be opened on 6th May 2015

17th Apr 2015

Tender will be opened on 18th May 2015-“CONSTRUCTION OF BRIDGES (INCLUDING RAIL-OVER-BRIDGE OVER CONCOR SIDING AT KHAPRI). "

1st Apr 2015

DMRC, RITES are appointed as interim consultant for Nagpur Metro Rail Project.

DMRC

  • Bid Process Management for Selection of General Consultant
  • Preparation of Schedule of Dimensions.
  • Preparation of Design Basis Report.

RITES

  1. Review of DPR in regard to traction type, coach width, platform length, and train length and critical review of alignment particularly as below but not restricted to:

  2. a)  Interchange station building at Munje Chowk with parking integration.

    b)  Chatrapati Nagar Square with station

    c)  Alignment between IGGMC & railway station on East-West corridor

    d)  Cotton Market Square to Anand talkies

    e)  Prajapati Nagar Square (junction of Ring Road & Bhandara Road)

    f)  CONCOR siding in MIHAN.

  3. Preparation of bid document & bid process management for appointment of execution agency for priority section between Airport – Khapri MIHAN (excluding depot)

  4. Preparation of bid documents for design & build viaduct portion of first elevated reach between Airport and Sitaburdi interchange (Munje Chawk).

  5. Provide GFC drawings for the priority section

  6. Preparation of bid document & bid process management for appointment of DDC (Detailed design Consultant including structural & architectural both) for stations including appointment of Architect for the interchange station (Sitaburdi).

27th March 2015

French Delegation visited Nagpur for detailed study of Nagpur Metro Rail Project

22nd Feb 2015

Agreement with DMRC for preparation of DPR

18th Feb 2015

Incorporation Of Nagpur Metro Rail Corporation Limited

12th Feb 2015

MADC transfered 37 ha land to NMRCL that includes land required for Depo

11th Feb 2015

Possession of 37.40 HR land out of 45.89 HR in MADC handed over to NMRCL

21st Aug 2014

‘Bhoomipujan’ Ceremony at the Hands of Hon. Prime Minister

21st Aug 2014

Approval of GoI to the project

11th Feb 2014

In Principle approval by MoUD, GoI

30th Jan 2014

Draft DPR approved by the State Government

May 2013

Traffic Survey